from the data above, compute the prime cost. 

  N
Direct material 2,500
Direct labour 5,000
Direct expenses 1,000
Overhead expenses 1,500

use the information contained in the table to anwser the qustion below;

from the data above, compute the prime cost. 

  • A.
    N6,500
  • B.
    N 8,500
  • C.
    N6,000
  • D.
    N7,500
Correct Answer: Option B
Explanation

Prime cost is the direct cost of a commodity in terms of the materials and labour involved in its production, excluding fixed costs. from the table above, prime cos is derivrd thus; Prime cost = direct material + direct labour + direct expenses 

2,500+5,000+1,000=8,500