A plank is placed along the path on which a wheel barrow containing sand is…

A plank is placed along the path on which a wheel barrow containing sand is pushed at a construction site to prevent it from sticking as illustrated in the diagram given. The large area of the plank prevents the wheel barrow from getting stuck by
  • A.
    increasing the reaction on the ground
  • B.
    increasing the pressure on the ground
  • C.
    decreasing the pressure on the ground
  • D.
    decreasing the weight on the ground
Correct Answer: Option C